  1. July 2010 Main building construction started
  2. October 2010 Satellite pier construction started
  3. November 2010 Old Terminal 2 demolished
  4. April 2011 Terminal 2 foundations complete
  5. September 2011 Multi-storey car park construction started
  6. December 2011 Terminal 2 superstructure complete
  7. February 2012 Terminal 2 becomes weathertight
  8. Summer 2012 Interior fit-out starts and satellite pier becomes weathertight
  9. Spring 2013 Terminal 2 systems installation begins
  10. Summer 2013 Multi-storey car park ready for operational trials
  11. Autumn / Winter 2013 Terminal 2 ready for operational trials
  12. June 4 2014 Terminal 2, its satellite pier and car park ready for passengers